Project Managment & Methods
|
Major restructuring program of a pharmaceutical distribution centre
Distribution centre for pharmaceutical products - Works without interruption of ongoing operation - Project lead of the general planner
|
|
Typology :
|
Industrial: Pharmaceutical distribution
|
Status :
|
Completed
|
City :
|
Ecublens, VD, Switzerland
|
Area :
|
9'798 m², Restructuration, IPMS2 (interiors)
|
Budget :
|
CHF 13'000'000, Excl. VAT
|
Client :
|
Galexis AG, Private entity
|
Mission :
|
- Ph. 3 PROJECT PLANNING
- Ph. 4 TENDER
- Ph. 5 REALISATION
|
Project pilot :
|
CSD Ingénieurs SA
Responsible: Roman Schirmer, Architect
|
|
General planning
|
- Management and coordination
- Resource management and monitoring
- Coordination of the specialised professionals, transdisciplinary monitoring of the objectives defined with the client. Management of contracts and monitoring of the services provided by the specialised professionals.
- Cost management
- Establishment and management of the general timetable. Monitoring of deadlines.
- Contracts for work
- General management of the work
- Cost control and expenditure monitoring
- Construction scheduling
|
|
Partners :
|
Éo architectes SA
Responsible: Héléna Carnal, Architect
|
www.eo-architectes.ch
|
Architecture
|
|
Perrin Spaeth - Bureau dingénieurs conseils SA
Responsible: Joseph La Luna
|
www.perrin-spaeth.ch
|
Electrical engineering
|
|
|
Execution of the works :
|
ADV Constructions SA
|
|
Civil engineering works, Masonry
|
|
Morand SA
|
|
Steel structure, Facade building
|
|
Ciel électricité SA
|
|
Electrics
|
|
Tecton Etanchéité SA
|
|
Waterproofing, Roofing
|
|
|
|
03.2019
-
09.2020
|
ZAC Porte de Paris - Transport hub
Responsible for the grafic synthesis - Conflict analysis, synthesis and coordination of execution planning Civil engineering / Underground / Tramway / Urban networks
|
|
Typology :
|
Urban Infrastructure
|
Status :
|
Completed
|
City :
|
Saint-Denis, IDF, France
|
Area :
|
17ha
|
Client :
|
SEM Plaine Commune Development, Public
|
Client :
|
Ingérop Management SAS, Private entity
|
Mission :
|
|
Project pilot :
|
Ingérop Management SAS
Responsible: Jean-Christophe Vigné & Marc Bourgeois
|
www.ingerop.fr
|
Project management
|
- Management and coordination
- Coordination of studies
- Technical synthesis
|
|
Consultants :
|
SEA - Sustainably Engineering Architecture
Responsible: Roman Schirmer, Architect
|
sea.archi
|
Project management
|
- Coordination of studies
- Technical synthesis
|
|
|
04.2011
-
08.2013
|
VINCI - Chantiers Modernes
Programming of an Rhinoceros Layermanager with Excel-Interface
This tool was required for the planning coordination in the context of the restructuring of the "Halles" in the 1st arrondissement of Paris. It allows the automatic normalisation of the 3D models received from the different participants before their integration into the coordination model.
More specifically, this application allows the management of layers in Rhinoceros files via MS Excel and the automatic modification of these layers according to a standard developed for the project. The application was programmed in Visual Basic for Applications (VBA).
|
|
Typology :
|
Methods : Management
|
Status :
|
Completed
|
City :
|
Paris, France
|
Client :
|
SEMAVIP, Public
|
Client :
|
Les Chantiers Modernes BTP, VINCI-Construction, Private entity
|
Mission :
|
|
Project pilot :
|
|
Consultants :
|
SEA - Sustainably Engineering Architecture
Responsible: Roman Schirmer, Architect
|
sea.archi
|
|
|
|
|
|
ZAC des Batignolles - Construction of an urban slab of 550 x 70m
Responsible for the grafic synthesis
|
|
Typology :
|
Urban Infrastructure
|
Status :
|
Completed
|
City :
|
Paris, France
|
Area :
|
6 ha
|
Client :
|
SNCF - Ville de Paris, Public
|
Client :
|
Ingérop-Management SAS, Private entity
|
Mission :
|
|
Participation :
|
Mission for the SNCF as a subcontractor of Ingérop-Management.
|
Project pilot :
|
Ingérop Management SAS
Responsible: Olivier Mollard, Civil Engineer
|
www.ingerop.fr
|
Project management
|
- Management and coordination
|
|
Consultants :
|
SEA - Sustainably Engineering Architecture
Responsible: Roman Schirmer, Architect
|
sea.archi
|
Project management
|
- Coordination of studies
- Technical synthesis
- Technical coordination
|
|
|
08.2009
-
01.2012
|
Charta für grafische Arbeiten
Setting up a methodological tool
By creating a work methodology in AutoCAD, we aimed to improve the quality of file exchanges between the company's employees and its partners. To enable everyone to quickly understand the content of a drawing file and to be able to modify it while remaining within the same work logic.
In addition to the fluidity of exchanges, the charter aimed to guarantee the quality of drawings for display and printing and the quality of project presentations through the uniformity of the drawings produced by the various participants.
This mission was concluded by a methodological note, by the implementation of templates and standard documents as well as by training sessions given to the company's employees.
|
|
Typology :
|
Methods : Management
|
Status :
|
Completed
|
City :
|
Paris, France
|
Client :
|
CLC Gestion de projet et conseil / Ingérop-Management SAS, Private entity
|
Project pilot :
|
SEA - Sustainably Engineering Architecture
Responsible: Roman Schirmer, Architect
|
sea.archi
|
|
|
|
|
|
Architecture & Engineering
|
Distillerie de Saconnex-d'Arve
Le bâtiment de la distillerie, destiné à un usage industriel et commercial, héberge actuellement trois exploitants : un brasseur, une cave à vin et une distillerie. Il comprend une boutique ouverte au public ainsi qu'un espace de bureaux partagé, qui abrite également les vestiaires et les sanitaires.
L'ensemble du bâtiment a été reconstruit tout en préservant les éléments du gros-œuvre en béton armé et une charpente métallique. Les parties restantes du bâtiment, partiellement contaminées par des polluants, ont été démolies après élimination de l'amiante, des PCB et du plomb.
Le volume reconstruit est principalement composé de bois, avec des éléments hybrides bois-béton. Dans une optique d'économie et de durabilité, l'utilisation de matériaux biosourcés a été privilégiée, notamment la laine de bois pour l'isolation. Les matériaux sont largement laissés bruts, limitant ainsi le recours à des produits de finition.
Commandé par la commune de Plan-les-Ouates, le projet est réalisé en entreprise totale. En qualité de sous-traitant, SEA a été investi de la responsabilité du développement technique à partir d'un avant-projet. Notre mandat impliquait la finalisation du projet en vue du lancement des appels d'offres (phase 41), puis son affinement ultérieur en prévision de la phase d'exécution (phase 51), aboutissant avec l'établissement des plans de recollement (phase 53) une fois les travaux achevés.
Cette mise au point technique s'est déroulée en étroite collaboration avec divers mandataires spécialisés, incluant l'ingénieur civil, le physicien du bâtiment, l'ingénieur CVSE et l'expert AEAI.
Les procédures d'appel d'offres ont été conduites en stricte conformité avec les principes fondamentaux du droit des marchés publics, en accord avec les exigences du cahier des charges.
Par ailleurs, le projet a été élaboré en employant la méthode BIM, ce qui a permis de renforcer notre expertise dans son application, particulièrement durant la phase de réalisation. (fr)
|
|
Typology :
|
Industrial and commercial buildings
|
Status :
|
Completed
|
City :
|
Saconnex-d'Arve (GE), Switzerland
|
Area :
|
954 m², Construction, IPMS 3C (interiors)
|
Budget :
|
CHF 2'250'000, Incl. VAT
|
Client :
|
Commune de Plan-les-Ouates, Public
|
Client :
|
Batineg SA, Private entity
|
Mission :
|
- Ph. 3 PROJECT PLANNING
- Ph. 4 TENDER
- Ph. 5 REALISATION
|
Partners :
|
SEA - Sustainably Engineering Architecture
Responsible: Roman Schirmer, Architect, Civil Engineer
|
sea.archi
|
Architecture
|
- Technical development
- BIM modelling
- Tender plans
- Technical development and elaboration of implementation details
- Implementation plans
|
INGEA SA
Responsible: Rui Pedro Sales Sério Lourenço, Civil Engineer
|
ingea.ch/
|
Civil engineering
|
|
Despres Études Énergétiques
Responsible: Alain Després, Engineer
|
despres.ch
|
Indoor climate
|
|
|
|
12.2021
-
02.2024
|
Sihlsteg Spinnerei - Construction of a bridge for light traffic
Competition Civil Engineering : Bridge made of steel, wood and natural stone
|
|
Typology :
|
Civil engineering : bridges
|
Status :
|
Study
|
City :
|
Langenau am Albis, ZH, Switzerland
|
Client :
|
Kanton Zürich, Public
|
Mission :
|
|
Participation :
|
Partnership with Maffeis & Equibridges AG. Concept proposal and development, landscape integration, formal design
|
Project pilot :
|
Maffeis Engineering GmbH
Responsible: Stefano Rossi, Architect
|
www.maffeis.it
|
|
- Management and coordination
|
|
Partners :
|
SEA - Sustainably Engineering Architecture
Responsible: Roman Schirmer, Architect, Civil Engineer
|
sea.archi
|
Architecture, Civil engineering
|
- Analysis of the urban, landscape and natural context. Formulation of the project's integration principles.
- Sketch/conceptual design: analysis of intentions, needs and programme in the development of an architectural concept translated into a sketch.
- Structural concept
- Structural design
|
Equi Bridges AG
Responsible: Poul Schroeder, Civil Engineer
|
equibridges.ch
|
Civil engineering
|
- General timetable
- Structural design
|
|
|
03.2021
-
04.2021
|
Extension of Chur West station - Railway viaduct
Construction of the bridge for the new railway station
|
|
Typology :
|
Civil engineering : bridges
|
Status :
|
Study
|
City :
|
Chur, GR, Switzerland
|
Client :
|
Rhätische Bahn, Public
|
Mission :
|
|
Participation :
|
In partnership with Equibridges AG. Contribution to the formal development of the project.
|
Project pilot :
|
Equi Bridges AG
Responsible: Poul Schroeder, Civil Engineer
|
equibridges.ch
|
Civil engineering
|
- Proposal for organisation and division of tasks.
- Estimation of administrative, study and construction costs.
- Preliminary timetable for studies and implementation, highlighting the impact of changes.
- Clarification of the technical, legal, economic and environmental framework. Concept proposal and feasibility check.
- Structural concept
- Structural design
|
|
Partners :
|
SEA - Sustainably Engineering Architecture
Responsible: Roman Schirmer, Architect, Civil Engineer
|
sea.archi
|
Architecture, Civil engineering
|
- Digital modelling
- Analysis and definition: needs, problems, requirements, risks. Report describing requirements and methodological approach.
- Structural design
|
Flender Generalplaner
Responsible: Kai Flender, Architect
|
www.kaiflender.de
|
Architecture
|
- Preparation of the project specifications.
|
Damien Lamoly
Responsible: Damien Lamoly, Technician
|
|
|
|
|
|
11.2020
-
12.2020
|
Renovation, extension and modernisation of an historical builing
Zürich villa of the early 19th century used as an office building - Site in use during the works
|
|
Typology :
|
Listed buildings : Conversion
|
Status :
|
Completed
|
City :
|
Zürich, Switzerland
|
Area :
|
1100 m²
|
Budget :
|
CHF 1'800'000, Excl. VAT, Restructuration
|
Mission :
|
- Ph. 4 TENDER
- Ph. 5 REALISATION
|
Project pilot :
|
Santiago Calatrava GmbH
Responsible: Roman Schirmer, Architect
|
calatrava.com
|
Architecture
|
- Preliminary schedule of works
- Building specifications
- Analysis and comparison of offers
- Tender plans
- Contracts for work
- Coordinated construction schedule
- Description, presentation and coordination of the execution project
- Technical development and elaboration of implementation details
- Implementation plans
- Cost control and expenditure monitoring
- Construction scheduling
- Site works supervision
|
Gerrit Teufel, Architect
|
|
|
- Management and coordination
|
|
Execution of the works :
|
KESSLER Bauunternehmung AG
Responsible: Reto Kessler
|
kesslerbau.ch
|
Civil engineering works
|
|
DE CAPITANI Baugeschäft AG
Responsible: Roger Schmid
|
www.decapitanibau.ch
|
Masonry
|
|
Max Keller AG
Responsible: Jorge Perez
|
mk-klima.ch
|
Air conditioning, MCR (Measurement, Control and Regulation), Ventilation
|
|
|
|
03.2018
-
03.2019
|
Chicago O'Hare International Airport
New Terminal 2
|
|
Typology :
|
Public : Airports
|
Status :
|
Study
|
Client :
|
Chicago Department of Aviation, Public
|
Mission :
|
|
Project pilot :
|
Santiago Calatrava GmbH
Responsible: Santiago Calatrava, Architect, Civil Engineer
|
calatrava.com
|
Architecture
|
|
Roman Schirmer, Architect
|
|
|
- Technical drawing
- Digital modelling
|
|
|
|
Reconstruction of the Morandi Bridge in Genoa
Cable-stayed bridge
|
|
Typology :
|
Civil engineering : bridges
|
Status :
|
Study
|
City :
|
Genoa, It
|
Budget :
|
226'000'000 €, Excl. VAT, Construction
|
Client :
|
Reconstruction commissioner of the collapsed Morandi bridge, Public
|
Mission :
|
|
Project pilot :
|
Santiago Calatrava GmbH
Responsible: Santiago Calatrava, Architect, Civil Engineer
|
calatrava.com
|
|
|
Roman Schirmer, Architect
|
|
|
- Technical drawing
- Digital modelling
- Parametric design
|
|
|
10.2018
-
12.2018
|
Contournement routier de Grüningen (Concours – Projet lauréat) (fr)
Vous pouvez trouver des informations plus amples au sujet du projet sur la page de l’Office des transports du canton de Zurich en suivant ce lien. (fr)
|
|
Typology :
|
Civil engineering : bridges
|
Status :
|
Study
|
City :
|
Grüningen, Zürich, Switzerland
|
Budget :
|
CHF 24'000'000
|
Client :
|
Kanton Zürich, Public
|
Mission :
|
|
Project pilot :
|
Santiago Calatrava GmbH
Responsible: Roman Schirmer, Architect
|
calatrava.com
|
Architecture
|
- Determination of organisation, division of tasks and data exchange standards.
- Sketch/conceptual design: analysis of intentions, needs and programme in the development of an architectural concept translated into a sketch.
- Pre-project: refinement of the sketch with the help of experts. Drawing up a construction and material concept.
- Landscape design
- Development of the road project: alignments, longitudinal and cross-sections, connections.
|
Manuel Zoller, Architect
|
|
|
- Management and coordination
|
|
|
|
Creek Harbour Tower
|
|
Typology :
|
Public : Other buildings
|
Status :
|
Ongoing
|
Client :
|
EMAAR, Private entity
|
Mission :
|
|
Project pilot :
|
Santiago Calatrava GmbH
Responsible: Santiago Calatrava, Architect, Civil Engineer
|
calatrava.com
|
Architecture
|
|
Roman Schirmer, Architect
|
|
|
- Technical drawing
- Digital modelling
- Parametric design
|
|
|
01.2018
-
03.2018
|
UAE Pavillion EXPO 2020 Dubai
|
|
Typology :
|
Public : Exposition spaces
|
Status :
|
Completed
|
Mission :
|
- Ph. 3 PROJECT PLANNING
- Ph. 4 TENDER
|
Project pilot :
|
Santiago Calatrava GmbH
Responsible: Santiago Calatrava, Architect, Civil Engineer
|
calatrava.com
|
|
|
Roman Schimer, Architect
|
|
|
- Technical drawing
- Digital modelling
- Parametric design
|
|
|
03.2017
-
01.2018
|
Grand Paris Express – Gares de Créteil l’Échat et de Saint-Maur Créteil (fr)
|
|
Typology :
|
Public : Train Stations
|
Status :
|
Completed
|
City :
|
Ile-de-France, France
|
Area :
|
Créteil : 8700 m², Construction, IPMS1 (interiors)
|
Area :
|
St-Maur : 9000 m², Construction, IPMS1 (interiors)
|
Client :
|
Société du Grand Paris, Public
|
Mission :
|
|
Project pilot :
|
|
Partners :
|
ANMA - Architectes et Urbanistes
Responsible: Jean-François Vaudeville, Architect
|
anma.fr
|
Architecture
|
- Management and coordination
|
Nicolas Beyret, Architect
|
|
|
|
Roman Schirmer, Architect
|
|
|
- Technical development and elaboration of implementation details
|
Hugh Dutton Associés
|
www.hda-paris.com
|
Civil engineering
|
|
|
|
|
Abondant 3 - Construction of a low-energy house
The garden and its house, a spatial continuum.
Three principles have significantly determined the development of the project.
1. energy efficiency: geothermal energy, use of natural solar radiation and efficient thermal insulation.
2. perceptible and functional continuity of the living space beyond the building envelope.
3. integration into the context through the analysis and reinterpretation of local typologies.
The chosen cross-section profile, a roof that sits directly on the ground, is inspired by traditional agricultural buildings of the region, whose flat tiled roofs become the façade.
This cross-section profile is relatively compact. It offers a low envelope-to-volume ratio, favouring the thermal insulation of the building.
The orientation of the building favours the relationship to the south.
The north façade on the site boundary consists of a large tile roof pitched at 45°. Heavily insulated, it protects the building and the garden from the prevailing rain winds and cold.
The south façade opens onto the landscape garden. It has a 60° slope to make the most of passive solar radiation. The façade is equipped with devices that allow the incoming radiation to be regulated in winter and blocked in summer.
The spatial continuity between inside and outside is emphasised by the arrangement of small volumes (sanitary facilities, outdoor workshop, outdoor bicycle shelter), fixed furniture (kitchen sideboard and cupboard for the heating system), by the continuity of the floor, the continuity of the wooden structure, echoes to indoor elements outside, such as the lighting fixtures.
Even in winter, when the windows are closed, the perception of the living space is extended. It extends to the boundaries of the garden.
|
|
Typology :
|
Housing : Houses
|
Status :
|
Completed
|
City :
|
Dreux, Eure et Loire, France
|
Area :
|
171 m², IPMS1 (interiors)
|
Budget :
|
380.000 €, Excl. VAT, Construction
|
Mission :
|
- Ph. 1 STRATEGIC PLANNING
- Ph. 2 PRELIMINARY STUDIES
- Ph. 3 PROJECT PLANNING
- Ph. 4 TENDER
- Ph. 5 REALISATION
|
Project pilot :
|
SEA - Sustainably Engineering Architecture
Responsible: Roman Schirmer, Architect
|
sea.archi
|
Architecture
|
- Management and coordination
- Setting up the project duty booklet
- Coordination of studies
- Management
- Cost management
- Establishment and management of the general timetable. Monitoring of deadlines.
- Project design
- Technical development
- Graphical representation
- Site works supervision
|
|
Partners :
|
Jean-Baptiste Fourmont Architecte
|
|
|
- Cost management
- Project design
- Site works supervision
|
|
Execution of the works :
|
|
|
10.2011
-
10.2016
|
Heavy restructuring of a 19th century building
Office building - Paris 9ème
|
|
Typology :
|
Offices : Building restructuring
|
Status :
|
Completed
|
City :
|
Paris, France
|
Area :
|
1450 m², Restructuration, IPMS1 (interiors)
|
Budget :
|
1'650'000 €, Excl. VAT, Restructuration
|
Client :
|
AEW Europe, Private entity
|
Mission :
|
- Ph. 51 Execution planning
- Ph. 52 Execution, works supervision
|
Project pilot :
|
Atelier Raf Listowski
Responsible: Roman Schirmer, Architect
|
www.raflistowski.com
|
Architecture
|
- Technical development and elaboration of implementation details
- Implementation plans
- Construction scheduling
- Site works supervision
|
|
|
03.2016
-
09.2016
|
House at the rock
|
|
Typology :
|
Housing : Houses
|
Status :
|
Study
|
City :
|
Magé, RJ, Brazil
|
Area :
|
135m², Construction
|
Budget :
|
350'000 R$, Excl. VAT, Construction
|
Mission :
|
- Ph. 2 PRELIMINARY STUDIES
- Ph. 3 PROJECT PLANNING
|
Project pilot :
|
SEA - Sustainably Engineering Architecture
Responsible: Roman Schirmer, Architect
|
sea.archi
|
|
- Clarification of the technical, legal, economic and environmental framework. Concept proposal and feasibility check.
- Calculation of volumes and areas. Cost estimate of the preliminary project +/- 15%.
- Sketch/conceptual design: analysis of intentions, needs and programme in the development of an architectural concept translated into a sketch.
- Pre-project: refinement of the sketch with the help of experts. Drawing up a construction and material concept.
|
|
|
06.2015
-
10.2015
|
Urban renewal project 'Porto Maravilha' : 'Prainha' Sector
Feasibility study
|
|
Typology :
|
Urban Renewal
|
Status :
|
Study
|
City :
|
Rio de Janeiro - RJ, Brazil
|
Area :
|
9.3 ha, Renovation
|
Client :
|
Consórcio Porto Novo, Private entity
|
Client :
|
GDP - Gerenciamento e Desenvolvimento de Projetos , Private entity
|
Mission :
|
- Ph. 21 Definition of the project, feasibility study
|
Project pilot :
|
GDP - Gerenciamento e Desenvolvimento de Projetos
Responsible: Sergio Leusin, Architect, Civil Engineer
|
www.gdp.arq.br
|
Architecture
|
- Management and coordination
|
Roman Schirmer, Architect
|
|
|
- Clarification of the technical, legal, economic and environmental framework. Concept proposal and feasibility check.
|
|
|
04.2015
-
08.2015
|
Urban renewal project 'Porto Maravilha' : 'Pedro Alves' Sector
Feasibility studies for 73 housing and office buildings
|
|
Typology :
|
Urban Renewal
|
Status :
|
Study
|
City :
|
Rio de Janeiro - RJ, Brazil
|
Area :
|
500m² - 7000m², Construction
|
Area :
|
79 450 m² / 73 Operations
|
Budget :
|
185'900'000 R$
|
Client :
|
Consórcio Porto Novo, Private entity
|
Client :
|
GDP - Gerenciamento e Desenvolvimento de Projetos, Private entity
|
Mission :
|
- Ph. 2 PRELIMINARY STUDIES
|
Project pilot :
|
GDP - Gerenciamento e Desenvolvimento de Projetos
Responsible: Sergio Leusin, Architect, Civil Engineer
|
www.gdp.arq.br
|
Architecture
|
- Management and coordination
|
Roman Schirmer, Architect
|
|
|
- Clarification of the technical, legal, economic and environmental framework. Concept proposal and feasibility check.
|
|
|
03.2014
-
03.2015
|
Project for the creation of an exhibition space in Rio de Janeiro downtown
|
|
Typology :
|
Public : Exposition spaces
|
Status :
|
Study
|
City :
|
Rio de Janeiro, RJ, Brazil
|
Area :
|
2000 m², Construction
|
Client :
|
GDP - Gerenciamento e Desenvolvimento de Projetos, Private entity
|
Mission :
|
- Ph. 21 Definition of the project, feasibility study
|
Project pilot :
|
SEA - Sustainably Engineering Architecture
Responsible: Roman Schirmer, Architect
|
sea.archi
|
Architecture
|
- Analysis and definition: needs, problems, requirements, risks. Report describing requirements and methodological approach.
- Clarification of the technical, legal, economic and environmental framework. Concept proposal and feasibility check.
|
|
|
01.2014
-
02.2014
|
Restructuring of the last storie of an apartment building in Paris
|
|
Typology :
|
Housing : Flats
|
Status :
|
Completed
|
City :
|
Paris, France
|
Area :
|
75m² , Restoration
|
Budget :
|
127.930 € HT
|
Mission :
|
- Ph. 2 PRELIMINARY STUDIES
- Ph. 3 PROJECT PLANNING
- Ph. 4 TENDER
- Ph. 5 REALISATION
|
Project pilot :
|
Jean-Baptiste Fourmont Architecte
|
|
Architecture
|
- Management and coordination
- Setting up the project duty booklet
- Management
- Cost management
- Establishment and management of the general timetable. Monitoring of deadlines.
- Project design
- Technical development
- Graphical representation
- Site works supervision
|
|
Partners :
|
SEA - Sustainably Engineering Architecture
Responsible: Roman Schirmer, Architect
|
sea.archi
|
Architecture
|
- Project design
- Technical development
- Graphical representation
|
|
|
|
Extension and transformation of a House around a Patio
|
|
Typology :
|
Housing : Extensions
|
Status :
|
Completed
|
City :
|
Paris, France
|
Area :
|
85m², Construction
|
Budget :
|
183'000 €, Excl. VAT
|
Mission :
|
- Ph. 2 PRELIMINARY STUDIES
- Ph. 3 PROJECT PLANNING
- Ph. 4 TENDER
- Ph. 5 REALISATION
|
Project pilot :
|
Jean-Baptiste Fourmont Architecte
|
|
Architecture
|
- Clarification of the technical, legal, economic and environmental framework. Concept proposal and feasibility check.
- Sketch/conceptual design: analysis of intentions, needs and programme in the development of an architectural concept translated into a sketch.
- Construction project: Elaboration of the construction project in view of the building application. Definition of construction principles and materials.
- Description, presentation and coordination of the execution project
- Technical development and elaboration of implementation details
- Implementation plans
- Cost control and expenditure monitoring
- Construction scheduling
- Site works supervision
|
|
Partners :
|
SEA - Sustainably Engineering Architecture
Responsible: Roman Schirmer, Architect
|
sea.archi
|
Architecture
|
- Clarification of the technical, legal, economic and environmental framework. Concept proposal and feasibility check.
- Sketch/conceptual design: analysis of intentions, needs and programme in the development of an architectural concept translated into a sketch.
- Construction project: Elaboration of the construction project in view of the building application. Definition of construction principles and materials.
- Description, presentation and coordination of the execution project
- Technical development and elaboration of implementation details
|
|
|
03.2011
-
07.2013
|
Low energy apartment building of 26 flats
Ecological clustered habitat
|
|
Typology :
|
Housing : Apartment buildings
|
Status :
|
Study
|
City :
|
Sceaux, IDF, France
|
Area :
|
1831 m², Construction, IPMS2 (interiors)
|
Budget :
|
2'968'500 €, Excl. VAT, Construction
|
Client :
|
Association Scéenne pour l'Habitat Participatif, Joint building venture
|
Mission :
|
|
Project pilot :
|
Atelier Kaba
Responsible: Hiroshi Naruse, Architect, Landscape Designer
|
www.atelierkaba.fr
|
Architecture
|
- Management and coordination
- Landscape design
|
|
Partners :
|
SEA - Sustainably Engineering Architecture
Responsible: Roman Schirmer, Architect
|
sea.archi
|
Architecture
|
- Analysis and definition: needs, problems, requirements, risks. Report describing requirements and methodological approach.
- Preparation of the project specifications.
- Estimation of administrative, study and construction costs.
- Clarification of the technical, legal, economic and environmental framework. Concept proposal and feasibility check.
- Sketch/conceptual design: analysis of intentions, needs and programme in the development of an architectural concept translated into a sketch.
|
Edouardo Rodriguez Architecte
Responsible: Edouardo Rodriquez, Architect
|
|
|
|
|
|
06.2013
-
07.2013
|
Roofs of Providence
Augmentation of a flat in Paris
|
|
Typology :
|
Housing : Extensions
|
Status :
|
Study
|
City :
|
Paris, France
|
Area :
|
34.1 m², Restructuration, IPMS 3C (interiors)
|
Area :
|
11.2 m², Terasse
|
Budget :
|
110'000 €, Excl. VAT, Restructuration
|
Mission :
|
- Ph. 2 PRELIMINARY STUDIES
- Ph. 3 PROJECT PLANNING
|
Project pilot :
|
SEA - Sustainably Engineering Architecture
Responsible: Roman Schirmer, Architect
|
sea.archi
|
|
|
|
|
10.2010
-
07.2013
|
Abondant 2 - Restructuration of a rural storing building in an two apartments house
|
|
Typology :
|
Housing : Apartment buildings
|
Status :
|
Completed
|
City :
|
Dreux, Eure et Loire, France
|
Area :
|
127 m², IPMS1 (interiors)
|
Budget :
|
117'200 €, Excl. VAT, Rehabilitation
|
Mission :
|
- Ph. 1 STRATEGIC PLANNING
- Ph. 2 PRELIMINARY STUDIES
- Ph. 3 PROJECT PLANNING
- Ph. 4 TENDER
- Ph. 5 REALISATION
|
Project pilot :
|
SEA - Sustainably Engineering Architecture
Responsible: Roman Schirmer, Architect
|
sea.archi
|
|
- Management and coordination
- Setting up the project duty booklet
- Coordination of studies
- Management
- Cost management
- Establishment and management of the general timetable. Monitoring of deadlines.
- Project design
- Technical development
- Graphical representation
- Site works supervision
|
|
Partners :
|
Jean-Baptiste Fourmont Architecte
|
|
|
- Cost management
- Project design
- Site works supervision
|
|
|
04.2011
-
06.2012
|
Lofts Arago
Conversion of a commercial building into 4 loft flats
|
|
Typology :
|
Housing : Apartment buildings
|
Status :
|
Completed
|
City :
|
Pantin, France
|
Budget :
|
201.700 €, Excl. VAT, Rehabilitation
|
Mission :
|
- Ph. 3 PROJECT PLANNING
- Ph. 4 TENDER
- Ph. 5 REALISATION
|
Project pilot :
|
Jean-Baptiste Fourmont Architecte
|
|
Architecture
|
|
|
Partners :
|
SEA - Sustainably Engineering Architecture
Responsible: Roman Schirmer, Architect
|
sea.archi
|
Architecture
|
|
|
|
10.2010
-
07.2011
|
Bioclimatic house-extension
Bioclimatic extension, integrated in the topography of its site.
Minimising intervention in the existing building in favour of a high-quality bioclimatic extension:
Our client, a couple about to retire, wanted to settle permanently in Néoules from the end of the current year, as they would be leaving their jobs in Paris.
Their biggest wish was to have a high-quality, comfortable and environmentally friendly house where they could live all year round.
The second important wish they expressed was to have space for their children, grandchildren and friends who would visit them regularly.
We then decided together that it would be economically advantageous to leave the existing pavilion more or less unchanged. Only light refurbishment work, consisting of bringing the electrics up to date, rethinking the interior distribution, creating openings to improve the connection with the extension, improving thermal comfort, especially by re-insulating the roof and adding external insulation, which was planned as a second phase.
Our work focused on the design of the extension, which will house the couple's permanent living space, while the existing living space would be used occasionally for friends and family.
|
|
Typology :
|
Housing : Houses
|
Status :
|
Study
|
City :
|
Néoules, Var, France
|
Area :
|
110, Construction, IPMS1 (interiors)
|
Area :
|
129, Restructuration, IPMS1 (interiors)
|
Budget :
|
289.000 €, Excl. VAT
|
Mission :
|
- Ph. 2 PRELIMINARY STUDIES
- Ph. 3 PROJECT PLANNING
|
Project pilot :
|
Jean-Baptiste Fourmont Architecte
|
|
|
- Estimation of administrative, study and construction costs.
- Calculation of volumes and areas. Cost estimate of the preliminary project +/- 15%.
- Sketch/conceptual design: analysis of intentions, needs and programme in the development of an architectural concept translated into a sketch.
- Pre-project: refinement of the sketch with the help of experts. Drawing up a construction and material concept.
- Estimate of costs +/- 10%.
- Construction project: Elaboration of the construction project in view of the building application. Definition of construction principles and materials.
|
|
Partners :
|
SEA - Sustainably Engineering Architecture
Responsible: Roman Schirmer, Architect
|
sea.archi
|
|
- Preparation of the project specifications.
- Compilation of basic data and decision protocol.
- Clarification of the technical, legal, economic and environmental framework. Concept proposal and feasibility check.
- Preliminary clarifications with official bodies. Protocol of decisions.
- Sketch/conceptual design: analysis of intentions, needs and programme in the development of an architectural concept translated into a sketch.
- Pre-project: refinement of the sketch with the help of experts. Drawing up a construction and material concept.
- Construction project: Elaboration of the construction project in view of the building application. Definition of construction principles and materials.
|
|
|
04.2011
-
07.2011
|
Abondant 1 - Transformation of a farmhouse in a two-family house
|
|
Typology :
|
Housing : Houses
|
Status :
|
Completed
|
City :
|
Dreux, Eure et Loire, France
|
Area :
|
118 m², Restructuration, IPMS1 (interiors)
|
Budget :
|
53'100 €, Excl. VAT
|
Mission :
|
- Ph. 1 STRATEGIC PLANNING
- Ph. 2 PRELIMINARY STUDIES
- Ph. 3 PROJECT PLANNING
- Ph. 4 TENDER
- Ph. 5 REALISATION
|
Project pilot :
|
SEA - Sustainably Engineering Architecture
Responsible: Roman Schirmer, Architect
|
sea.archi
|
|
- Management and coordination
- Setting up the project duty booklet
- Coordination of studies
- Management
- Cost management
- Establishment and management of the general timetable. Monitoring of deadlines.
- Project design
- Technical development
- Graphical representation
- Site works supervision
|
|
Partners :
|
Jean-Baptiste Fourmont Architecte
|
|
|
- Cost management
- Project design
- Site works supervision
|
|
|
03.2011
-
07.2011
|
Loft conversion and creation of a roof deck
Small intervention in the historic district 'Butte aux Cailles' in Paris.
|
|
Typology :
|
Housing : Terrace
|
Status :
|
Completed
|
City :
|
Paris, France
|
Area :
|
40m², Restructuration, IPMS1 (interiors)
|
Budget :
|
40.000€, Excl. VAT, Restructuration
|
Mission :
|
- Ph. 3 PROJECT PLANNING
- Ph. 4 TENDER
- Ph. 5 REALISATION
|
Project pilot :
|
SEA - Sustainably Engineering Architecture
Responsible: Roman Schirmer, Architect
|
sea.archi
|
Architecture
|
- Cost management
- Establishment and management of the general timetable. Monitoring of deadlines.
- Project design
- Technical development
- Graphical representation
- Site works supervision
|
|
|
02.2009
-
06.2011
|
Loft in Pantin near Paris
Transformation of a hangar into a rental flat and a Loft
|
|
Typology :
|
Housing : Transformation
|
Status :
|
Completed
|
City :
|
Pantin, IDF, France
|
Area :
|
160 m², Restructuration, IPMS1 (interiors)
|
Budget :
|
113'000 €, Excl. VAT
|
Mission :
|
- Ph. 2 PRELIMINARY STUDIES
- Ph. 3 PROJECT PLANNING
|
Project pilot :
|
Jean-Baptiste Fourmont Architecte
|
|
|
- Management and coordination
- Project design
- Technical development
- Graphical representation
|
|
Partners :
|
SEA - Sustainably Engineering Architecture
Responsible: Roman Schirmer, Architect
|
sea.archi
|
|
- Technical development
- Graphical representation
- Survey of the existing
|
|
|
02.2011
-
04.2011
|
Maisons groupés Karman
Feasibility study for individual grouped housing
|
|
Typology :
|
Housing : Apartment buildings
|
Status :
|
Completed
|
City :
|
Aubervilliers, France
|
Area :
|
585 m²
|
Budget :
|
366.000 €
|
Project pilot :
|
Jean-Baptiste Fourmont Architecte
|
|
|
- Setting up the project duty booklet
- Project design
|
|
Partners :
|
SEA - Sustainably Engineering Architecture
Responsible: Roman Schirmer, Architect
|
sea.archi
|
|
|
|
|
02.2011
-
03.2011
|
Au pied de Montmartre
Renovation of a Parisian roof-flat
|
|
Typology :
|
Housing : Flats
|
Status :
|
Completed
|
City :
|
Paris, France
|
Area :
|
33 m², IPMS 3C (interiors)
|
Budget :
|
18.000 €, Excl. VAT, Renovation
|
Mission :
|
- Ph. 3 PROJECT PLANNING
- Ph. 4 TENDER
- Ph. 5 REALISATION
|
Project pilot :
|
SEA - Sustainably Engineering Architecture
Responsible: Roman Schirmer, Architect
|
sea.archi
|
|
- Establishment and management of the general timetable. Monitoring of deadlines.
- Project design
- Technical development
- Graphical representation
- Site works supervision
|
|
|
09.2010
-
11.2010
|
Traditional Japanese house
|
|
Typology :
|
Housing : Houses
|
Status :
|
Study
|
Area :
|
380 m², IPMS1 (interiors)
|
Budget :
|
1.200.000 €, Excl. VAT, Construction
|
Mission :
|
- Ph. 2 PRELIMINARY STUDIES
- Ph. 3 PROJECT PLANNING
|
Project pilot :
|
Atelier Kaba
Responsible: Hiroshi Naruse, Architect, Landscape Designer
|
www.atelierkaba.fr
|
Architecture
|
- Management and coordination
- Project design
|
|
Partners :
|
SEA - Sustainably Engineering Architecture
Responsible: Roman Schirmer, Architect
|
sea.archi
|
|
- Technical development
- Graphical representation
|
|
|
01.2010
-
03.2010
|
Bouchardon Flat Restructuring
Transformation of a Parisian Flat in a '1900' Building.
|
|
Typology :
|
Housing : Flats
|
Status :
|
Completed
|
City :
|
Paris, France
|
Area :
|
130 m², IPMS 3C (interiors)
|
Budget :
|
93.000 €, Excl. VAT, Restructuration
|
Mission :
|
- Ph. 2 PRELIMINARY STUDIES
- Ph. 3 PROJECT PLANNING
- Ph. 4 TENDER
- Ph. 5 REALISATION
|
Project pilot :
|
SEA - Sustainably Engineering Architecture
Responsible: Roman Schirmer, Architect
|
sea.archi
|
|
- Setting up the project duty booklet
- Cost management
- Establishment and management of the general timetable. Monitoring of deadlines.
- Project design
- Technical development
- Graphical representation
- Site works supervision
|
|
Partners :
|
Jean-Baptiste Fourmont Architecte
|
|
|
- Graphical representation
- Site works supervision
|
|
|
05.2009
-
01.2010
|
Brasserie Télécommande
|
|
Typology :
|
Commercial : Restaurants
|
Status :
|
Study
|
City :
|
Paris, France
|
Area :
|
508 m²
|
|
02.2009
-
03.2009
|
Cristino-Garcia School
Kindergarden and primary school
|
|
Typology :
|
Public : Schools
|
Status :
|
Study
|
City :
|
Aubervilliers, France
|
Area :
|
6 303 m², IPMS1 (interiors)
|
Budget :
|
11'000'000 €, Excl. VAT, Construction
|
Client :
|
Communes de St-Denis et d’Aubervilliers, Public
|
Mission :
|
|
Project pilot :
|
Atelier Kaba
Responsible: Hiroshi Naruse, Architect, Landscape Designer
|
www.atelierkaba.fr
|
|
- Management and coordination
|
|
Partners :
|
SEA - Sustainably Engineering Architecture
Responsible: Roman Schirmer, Architect
|
sea.archi
|
|
|
|
|
09.2008
-
10.2008
|
Centre Culturel et des Congrès de Montrouge
Rehabilitation
|
|
Typology :
|
Public : Exposition spaces
|
Status :
|
Completed
|
City :
|
Montrouge, France
|
Area :
|
9 975 m2
|
Budget :
|
21,8 M €
|
Client :
|
Commune de Montrouge
|
Project pilot :
|
|
Partners :
|
SEA - Sustainably Engineering Architecture
Responsible: Roman Schirmer, Architect
|
sea.archi
|
|
- Technical development
- Graphical representation
|
|
|
04.2008
-
06.2008
|
Construction de deux immeubles de logement
|
|
Typology :
|
Housing : Apartment buildings
|
Status :
|
Completed
|
City :
|
Paris, France
|
Area :
|
6065 m²
|
Budget :
|
8,48 M€
|
Mission :
|
|
|
|
Ferme du Rancure
|
|
Typology :
|
Housing : Houses
|
Status :
|
Ongoing
|
City :
|
Alpes-de-Haute-Provence, France
|
Area :
|
250 m²
|
Budget :
|
Autoconstruction
|
Mission :
|
- Ph. 2 PRELIMINARY STUDIES
- Ph. 3 PROJECT PLANNING
|
Project pilot :
|
SEA - Sustainably Engineering Architecture
Responsible: Roman Schirmer, Architect
|
sea.archi
|
Architecture
|
|
|
|
11.2006
-
05.2007
|
Court of Justice Yvelines
Versailles
|
|
Typology :
|
Public : Other buildings
|
Status :
|
Study
|
City :
|
Versailles, France
|
Area :
|
11'000 m²
|
Budget :
|
40'500'000 €, Excl. VAT
|
Client :
|
Ministère de la Justice, Public
|
Mission :
|
|
Project pilot :
|
Vincent Brossy & Associés
Responsible: Michaël Fellmann, Architect
|
www.brossy.com
|
|
|
Roman Schirmer
|
|
|
- Technical development
- Graphical representation
- Physical model
|
|
|
01.2007
-
03.2007
|
Casbah House
|
|
Typology :
|
Housing : Extensions
|
Status :
|
Completed
|
City :
|
Tanger (Maroc)
|
|
09.2006
-
11.2006
|
Maison Marcais
|
|
Typology :
|
Housing : Houses
|
Status :
|
Study
|
City :
|
Entrevennes, Alpes-de-Haute-Provence, France
|
Area :
|
316 m², IPMS1 (interiors)
|
Budget :
|
470'000 €, Excl. VAT
|
Mission :
|
- Ph. 2 PRELIMINARY STUDIES
- Ph. 3 PROJECT PLANNING
|
Project pilot :
|
SEA - Sustainably Engineering Architecture
Responsible: Roman Schirmer, Architect
|
sea.archi
|
|
- Analysis and definition: needs, problems, requirements, risks. Report describing requirements and methodological approach.
- Clarification of the technical, legal, economic and environmental framework. Concept proposal and feasibility check.
- Sketch/conceptual design: analysis of intentions, needs and programme in the development of an architectural concept translated into a sketch.
|
|
|
08.2005
-
09.2005
|
School-building 'de la Gare'
|
|
Typology :
|
Public : Schools
|
Status :
|
Completed
|
City :
|
Paris , France
|
Area :
|
2700 m²
|
Budget :
|
3.8 M
|
|
02.2005
-
04.2005
|
Pavillon de l'eau
Conversion of the historical Auteil pumping stations into a public water information centre
|
|
Typology :
|
Public : Exposition spaces
|
Status :
|
Completed
|
City :
|
Paris, France
|
Area :
|
1200 m², IPMS2 (interiors)
|
Budget :
|
3'500'000 €, Excl. VAT, Rehabilitation
|
Client :
|
Ville de Paris, Public
|
Mission :
|
- Ph. 2 PRELIMINARY STUDIES
- Ph. 3 PROJECT PLANNING
- Ph. 4 TENDER
|
Project pilot :
|
Vincent Brossy & Associés
Responsible: Ivan Icart, Architect
|
www.brossy.com
|
Architecture
|
- Management and coordination
|
Roman Schirmer
|
|
|
- Technical development
- Graphical representation
- Survey of the existing
|
|
|
11.2004
-
12.2004
|
Bastide Saint-Michel
|
|
Typology :
|
Housing : Houses
|
Status :
|
Study
|
City :
|
Alpes-de-Haute-Provence, France
|
Mission :
|
- Ph. 1 STRATEGIC PLANNING
- Ph. 2 PRELIMINARY STUDIES
- Ph. 3 PROJECT PLANNING
|
Project pilot :
|
SEA - Sustainably Engineering Architecture
Responsible: Roman Schirmer, Architect
|
sea.archi
|
|
- Physical model
- Survey of the existing
- Analysis and definition: needs, problems, requirements, risks. Report describing requirements and methodological approach.
- Clarification of the technical, legal, economic and environmental framework. Concept proposal and feasibility check.
- Sketch/conceptual design: analysis of intentions, needs and programme in the development of an architectural concept translated into a sketch.
|
|
|
06.2004
-
08.2004
|
Bellevue House
Bioclimatic project in tropical ambient
|
|
Typology :
|
Housing : Houses
|
Status :
|
Study
|
City :
|
Martinique, France
|
Area :
|
118 m², IPMS1 (interiors)
|
Area :
|
46 m² Terrasse
|
Budget :
|
266'000 €, Excl. VAT, Construction
|
Mission :
|
- Ph. 1 STRATEGIC PLANNING
- Ph. 2 PRELIMINARY STUDIES
- Ph. 3 PROJECT PLANNING
|
Project pilot :
|
SEA - Sustainably Engineering Architecture
Responsible: Roman Schirmer, Architect
|
sea.archi
|
|
- Analysis and definition: needs, problems, requirements, risks. Report describing requirements and methodological approach.
- Clarification of the technical, legal, economic and environmental framework. Concept proposal and feasibility check.
- Sketch/conceptual design: analysis of intentions, needs and programme in the development of an architectural concept translated into a sketch.
- Pre-project: refinement of the sketch with the help of experts. Drawing up a construction and material concept.
- Construction project: Elaboration of the construction project in view of the building application. Definition of construction principles and materials.
|
|
|
01.2004
-
04.2004
|
Furniture
|
Shelf Rio
|
|
Typology :
|
Shelves
|
Status :
|
Completed
|
Format :
|
Solitary Objects
|
|
04.2016
-
07.2021
|
Cairos Offices
Modular system for the creation of an efficient working environnement
|
|
Typology :
|
Desks
|
Status :
|
Completed
|
Format :
|
Sets
|
|
01.2009
-
03.2009
|
Protoypes and Models
|
Model of the Bridge of Chateau Gontier
|
|
Typology :
|
Models
|
Status :
|
Completed
|
City :
|
Château-Gontier, France
|
|
04.2006
-
06.2006
|
Model of the 'Théâtre des Champs-Elysées'
Exhibitionmodel exposed in the 'Cité de l'Architecture et du Patrimoine' - Palais de Chaillot - Paris
|
|
Typology :
|
Models
|
Status :
|
Completed
|
City :
|
Paris, France
|
|
06.2002
-
09.2002
|